68 Manning St, Scarborough

Western Power required a material that could insulate noise and was highly fire resistant to house two power transformers. Hebel wall panels provided acoustic qualities of 50dB+Ctr and four hours fire resistance and were installed with minimal shut-down time.

Project Scope

100mm thick Hebel panels on structural steel frames

Build Time

Eight days

Project Value

$40,000

Builder

E&M Industries Pty Ltd